Progress Update
Soil corrections are complete and we continue to backfill along the foundation walls as the concrete foundations finish. CMU has started on the south stairwell and elevator shaft and steel erection has begun in the basement. We continue to work hard with a focus on safety!
Photo Update
Quality Corner
Maximum Allowable Variation: The maximum allowable variation from plumb or level for structural steel is 1/4″. Staying within this tolerance is very important for ensuring quality work in accordance to the plans and specs and preventing issues during construction on the project.
Upcoming Work
- Sequence 1 Structural Steel
- Interior pad footings
Did You Know?
In the basement, 8,920 square feet of form work has been used while forming the tall foundation walls.