Progress Update
Last week, the east CMU stairwell was completed while the north stairwell and Elevator shaft are ongoing. Sequence 1 steel erection in the south is nearly complete as we work on decking/detailing and pushing forward to the north erecting sequence 2. Lastly, In the south east, the steam and condensate piping installation has begun.
Photo Update
Quality Corner
Anchor Bolt As-Builts: As the concrete foundations are poured and the anchor bolts are placed, as-builts are performed. The as-builts determine if the anchor bolts were correctly placed or if they moved during the pour. Performing these as-builts helps minimize problems when setting steel and ensures quality work is being
Upcoming Work
-
Sequence 1 Steel Decking and detailing
-
Sequence 2 steel erection
-
North CMU Elevator Shaft and stairwell
-
Steam and Condensate piping
-
Slabs on deck/Grade
Did You Know?
So far 22,600 square feet of steel decking has been installed. This is the equivalent of 4 NBA basketball courts.
All comments will be reviewed prior to posting.