Progress Update
Last week we finished pouring the last foundation wall just in time for the Thanksgiving Holiday! The south CMU stairwell and elevator shaft are also complete! If you were to drive by the site this week you will see the building is really starting to take shape as we continue to set structural steel.
Photo Update
Quality Corner
Soil Density Tests: As the site gets backfilled, a third party inspector is brought in to perform soil density tests. These tests ensure the fill meets the compaction requirement. Ensuring proper compaction creates a solid bearing surface free of rutting or deflection and is safe for construction.
Upcoming Work
-
Skyway Piers
-
Sequence 1 Steel Decking and detailing
-
Sequence 2 steel erection
-
North CMU Elevator Shaft
Did You Know?
So far 10,595 square feet of CMU has been placed. This is the equivalent of approximately 4 full size tennis courts.
Would be informative to have a link to the architect’s drawing of the project to compare progress to the final product with each of these updates.
Hi Pam,
Here is a link to the Nistler College of Business & Public Administration Building Campaign. We will make sure to include a link in our future updates. Thank you!
Thank you very useful sharing. I’m a civil engineer