Nistler CoBPA Late May Progress Update

Progress Update

Installation of the sloped roof vapor barrier is continuing in Sequence 3. Installation of plywood and insulation on the sloped roof began earlier this week. Flat roof installation has been completed in Sequence 1 and is ongoing in Sequence 2. The atrium curtain wall installation began early last week. Exterior framing continues to move into Sequence 3. Sheathing on the west side has progressed into Sequence 3. Inside the building, ductwork installation continues to progress to the north on first, second, and third floor. Overhead mechanical, electrical, plumbing, and interior framing has started on 1st floor. On levels 2 and 3 work continues progressing north. Fire protection main installation began earlier last week in sequence 2 and 3.

Photo Update

Quality Corner

As we complete the last concrete slab pour, ensuring the quality of the finish on the slab and elevation is important. Throughout the concrete pour, multiple times the elevation is verified to ensure the top of the slab is at the correct elevation. As the concrete slab is setting up and is being finished, it is also important that the floor flatness is verified as this slab will be the substrate for the entry terrazzo floor!

Upcoming Work

  • Sequence 2 Duct installation

  • Sequence 2 Flat Roofing

  • Sequence 1 and 2 Sheathing, Blocking, and Air Barrier

  • Sequence 2 in wall rough-in

  • Sequence 3 slab pours

  • Sequence 1 insulation of mechanical pipes

  • West elevation window installation

  • Skyway concrete pours

Did You Know?

The UND Nistler College of Business has over 10,000 square yards of carpet. That’s over 5 ice sheets at The Ralph.

2 thoughts on “Nistler CoBPA Late May Progress Update

  • May 24, 2021 at 2:51 pm
    Permalink

    It appears that the Nistler Skyway will enter Merrifield Hall at the north end of the second floor. That means that it would emerge in Merrifield just outside the office of my father (Prof. Elwyn B Robinson) office! Will there be a continuation skyway that will cross University Ave?

  • May 25, 2021 at 10:52 am
    Permalink

    Thanks for your question Stephen! At this time we don’t have plans in place for a skywalk to cross University Ave at this location. This may be considered at some point in the future as the property on the north side of University Ave is developed.