UND Logo

Campus Renewal & Construction Updates

Updates on the construction of the Memorial Union other campus projects at the University of North Dakota.

Campus Renewal & Construction Updates

Menu

  • Updates
  • Memorial Union
  • Nistler CoBPA
  • Chester Fritz Library
  • Contact
  • Schedule an Event

Nistler CoBPA

Nistler CoBPA Early January Progress Update

vazzarello Building Updates, Nistler CoBPA January 5, 2021Construction, Nistler College of Business and Public Administration 0 Comment
Nistler CoBPA Early January Progress Update

Progress Update Structural steel erection continues in sequence 2 while we continue decking and detailing sequence 1. The CMU stairwell and elevator shaft in the north will be finished soon. The steam and condensate piping in the south end of site […]

Nistler CoBPA Late December Progress Update

vazzarello Building Updates, Nistler CoBPA December 21, 2020Construction, Nistler College of Business and Public Administration 0 Comment
Nistler CoBPA Late December Progress Update

Progress Update Last week, the east CMU stairwell was completed while the north stairwell and Elevator shaft are ongoing. Sequence 1 steel erection in the south is nearly complete as we work on decking/detailing and pushing forward to the north erecting […]

Nistler CoBPA Early December Progress Update

vazzarello Building Updates, Nistler CoBPA December 7, 2020Construction, Nistler College of Business and Public Administration 2 Comments
Nistler CoBPA Early December Progress Update

Progress Update Last week we finished pouring the last foundation wall just in time for the Thanksgiving Holiday! The south CMU stairwell and elevator shaft are also complete! If you were to drive by the site this week you will see […]

Nistler CoBPA Late November Progress Update

vazzarello Building Updates, Nistler CoBPA November 20, 2020Construction, Nistler College of Business and Public Administration 0 Comment
Nistler CoBPA Late November Progress Update

Progress Update Backfilling of the foundation continues as we push to complete concrete foundations. CMU in the south is nearly complete and will move to the east next to begin on the east stairwell. Structural steel erection has begun on the […]

Nistler CoBPA Early November Progress Update

vazzarello Building Updates, Nistler CoBPA November 6, 2020November 6, 2020Construction, Nistler College of Business and Public Administration 0 Comment
Nistler CoBPA Early November Progress Update

Progress Update Soil corrections are complete and we continue to backfill along the foundation walls as the concrete foundations finish. CMU has started on the south stairwell and elevator shaft and steel erection has begun in the basement. We continue to […]

Nistler CoBPA October Progress Update

vazzarello Building Updates, Nistler CoBPA October 27, 2020Construction, Nistler College of Business and Public Administration 3 Comments
Nistler CoBPA October Progress Update

Progress Update The basement foundation walls are complete which allows waterproofing and backfill to begin. Soil corrections resume in the north, footings and walls are being formed and poured on main level, and sequence 2 utilities are underway. The building will […]

Nistler CoBPA Progress Update

vazzarello Building Updates, Nistler CoBPA September 28, 2020Building, Construction, Nistler CoBPA 2 Comments
Nistler CoBPA Progress Update

Progress Update First concrete pour was last week and we are continuing to form basement walls and step up to the main level. Mass excavation and Soil correction continues, and waterproofing has begun in the basement. North view of site Forming first pour […]

Subscribe to our Updates

Filter by Topic

  • Building Updates
  • Chester Fritz Library
  • Dining
  • Gershman Graduate Center
  • McCannel Hall
  • Memorial Union
  • Nistler CoBPA
  • O'Kelly Hall
  • Parking & Transportation
  • Relocations
  • Road Construction
  • Twamley Hall
  • Wilkerson Commons

Memorial Union Construction Cameras

Launch Live Cams
Copyright © 2021 Campus Renewal & Construction Updates. Powered by WordPress. Theme: Accelerate by ThemeGrill.
Jump to header