With the closure of the Twamley Hall parking lot and UND ROTC programs relocated, the pedestrian routes in that area have changed. Current pedestrian routes are shown in GREEN.
Pedestrian Routes Change Near Twamley Hall

Progress Update Installation of the sloped roof vapor barrier is continuing in Sequence 3. Installation of plywood and insulation on the sloped roof began earlier this week. Flat roof installation has been completed in Sequence 1 and is ongoing in Sequence […]
The service drive and parking area between O’Kelly and Gillette will be closed Monday, May 24th for construction work at O’Kelly and Gillette Hall. Above is an exhibit showing the approximate limits of the closed service area. Please note that […]
Progress Update Installation of the sloped roof vapor barrier has begun on sequence 2 and 3. The sloped roof decking is complete. Sequence 1 flat roof installation has began this week with insulation being laid out and epdm Rubber Roofing adhered. […]
Columbia Road Project construction begins next week, with lane closures planned for the week of 5/10. Construction Crews plan to close the eastern most lanes of Columbia Road next week to begin the reconstruction project. Traffic will be shifted to […]
Photos from the latest project site walk. This is the eighth in a monthly photo update series for this academic calendar year. Be sure to visit the Campus Renewal Blog again next month for more photos of Memorial Union construction […]
Progress Update Installation of the sloped roof vapor retarder has begun on sequence 2 and 3. The sloped roof decking is ongoing in sequence 3. Level 4 clearstory walls are being framed and sheathed. Exterior framing is ongoing throughout the exterior. […]
The Twamley Hall parking lot will be closing on May 10th, 2021. UND ROTC programs will be relocating from the Armory to Twamley Hall early the week of May 17th and will remain there until early August. Pedestrian routes will […]
Progress Update The sloped roof vapor retarder has begun installation on sequence 2 and 3. The sloped roof decking is ongoing in sequence 3. Level 4 clerestory walls are being framed and sheathed. Exterior framing is ongoing throughout the exterior. Inside […]