Library Renovation: 4/29/19

At the end of the semester, more sections of the east side of the building will be closed as construction ramps up. Please heed all the construction signs that you see! The library itself will still be open and all services will continue as normal.

The bike racks will soon be moved outside the construction fence and will be available for student use.

Planned power outages will occur over the next several weeks, but we will post notices on the blog and social media and will put up signs around the building closer to each exact date and time.

Don’t forget that the north entry (on the University Ave. side of the street) will be closed starting on Monday, May 13.

What’s coming up?

  • We’re hoping to have second floor completely ready for students to return in the fall!
  • Furniture from the Memorial Union will be placed on the 2nd floor east and 3rd floor.
  • Many more electrical outlets will be added over the summer to the 2nd and 3rd floors.